Thermal oil Boiler Plant 8,2 MW
ORC- Organic Rankine Cycle –technlogy
Customer- local municipal heat producing company
Heat is delivered to district heating network
Project execution January 2012- December 2012
ORC- Organic Rankine Cycle –technlogy
Customer- local municipal heat producing company
Heat is delivered to district heating network
Project execution January 2012- December 2012

Main equipment
BFB type Boiler
ORC-turbine unit (thermal power 5,39 MW, electric power 1,269 MW)
Scope of supply
- Equipment, installation
- BFB boiler
- Fuel receiving and handling
- ESP and chimney
- Building &Steel Structures (excluding foundations)
- Process electrification and automation
- Building electrification
- Building HVAC
- Project management
- Commissioning
- Spare parts package